![]() The pad must be positioned so that around the branch, is overall the same open space, and that the pad is fully in line with the run pipe. Then the Reinforcing Pad can be placed by slide him over the branch.If de weld is ready, depending on the requirements Non Destructive Examination (NDE) must be done.Then the new branch can be completely welded. ![]() Place the branch with a gap by about 3 to 4 mm about the hole location on the run pipe, and tack weld the branch on a sufficient number of places.Finish the branch equal to outside diameter of run pipe and make a welding bevel of around 30Ā°.Determine the location of the branch, and make a round hole in the run pipe where the diameter should be equal to the inside diameter of the branch.Example for the assembly of a Reinforcing Pad.